FPL Undergrounding Program
November 30, 2022 Update
Completed 2019 2021
- 30 laterals
- 11.38 miles removed
- Approx. 494 Customers
Completed 2022
- 26 laterals
- 5.75 miles removed
- Approx. 303 customers
Pending from planned 2022
- 50 laterals
- 14.36 miles to be removed
- Approx. 741 customers
FPL advised that there have been some delay as the utility coordinates with the Villages water main project. FPL is working diligently to complete the outstanding projects as soon as possible.
FPL Undergrounding Maps(PDF, 444KB)
February 10, 2022 Update
Following are the statistics provided by FPL.
- Installed since program inception: 21 miles
- Planned for 2022: 50 miles
The plan for 2023 has not been finalized and wont be until the third or fourth quarter of 2022.
FPL Correspondence by date:
01/26/2022 Letter 1(PDF, 945KB), Letter 2(PDF, 557KB) , Letter 3(PDF, 822KB)
01/31/2022 Letter 1(PDF, 1MB) , Letter 2(PDF, 780KB) , Letter 3(PDF, 750KB)
02/08/2022 Letter 1(PDF, 674KB)
02/15/2022 Letter 1(PDF, 643KB)
02/22/2022 Letter1(PDF, 566KB)
August 2020 Update
FPL is currently undergrounding 20.1 miles of power lines in Pinecrest as part of a pilot program.
Watch Information Meeting - 8/27/20
FPL Contacts
Arturo Perez FPL Lead Customer Specialist
786-295-6504
Arturo.Perez@fpl.com
Javier Prado FPL Undergrounding Project Liaison
786-598-5341
Javier.Prado@fpl.com